Fix a plan as the baseline the year is measured against. Once a plan is approved, comparisons with actuals measure against it as it was that day, however much the working plan is edited afterwards.

Only the workspace's Owner can approve a plan.

Steps

  1. Open Plans and open the plan.

  2. Check the plan is the one you want to measure the year against: the numbers everyone agreed to, not a draft.

  3. Click Approve plan next to the plan's name.

    You should see a strip under the toolbar asking Approve … as it is now?

  4. Click Approve.

    You should see a green tag next to the plan's name, for example Approved 13 Nov 2026, and the message Approved. Comparisons with actuals now measure against the plan as it is now.

The plan stays editable. Changes go into the working plan; the approved baseline doesn't move.

Approving again

If the plan is formally revised (a mid-year re-forecast, say), approve it again: click Approve again and confirm. The new version becomes the baseline. The earlier one is kept, and every approval is recorded.

Common mistakes